Biofer

Location: Presov, Slovakia
Aqua feed: Raw material storage

30 M3 5.0 m

Project details

For Biofer, TSC expanded the raw material storage capacity by adding ten silo cells. Due to the dimensions of the silo block, it was decided to deliver it partially pre-assembled. The steel structure, hoppers, lower wall sections and slanting plates were assembled during production and then painted as a single unit. The main advantages were the shorter installation time and the relocation of all welding activities to during production, allowing the entire on-site installation to be carried out using only bolts and nuts.

Bins

10

Capacity

10 m3

Length

5,0 meter

Width

2,0 meter

Biofer, Presov Slovakia

Daan van Kempen

Account Manager
I went to Slovakia to take a look during the assembly of this project. The complete silo block was constructed in less than three days. This caused minimal disruption to Biofer's production process. What I like most about this project is that it is a good example of how flexible our silo system is, from small cells like this one to large silo blocks with hundreds of cubic meters per cell; anything is possible!
Want to know more? Mail to d.vankempen@tsc-silos.com or Call with +31683623602
Related projects

De Heus LLC

De Heus LLC
Location: Ving Long, Vietnam
Capacity: 30 bins
Aqua feed: Dosing
View project
2.125 M3 30.5 m
TSC - BioMar

BioMar Australia

BioMar Australia
Location: Wesley Vale, Tasmania, Australia
Capacity: 2.900 m³
Aqua feed: Dosing
View project
2.900 M3 29.8 m
Less Cost Waste
More Result Sustainability

Procedure

Procedure The regulations of the industry, the properties of the material, the geographical conditions of the construction site, the weather conditions in the region… we leave nothing to chance. We therefore work according to the TSC roadmap. This way, we work efficiently and do not overlook any detail. A solid approach for a solid result.

Questions? Contact us
Customized silo in 7 steps
  • In the first step, we discuss the requirements, capacity needs, external conditions and preconditions. What challenges should we take into account. Result: a programme of requirements; our basis.
  • Our concrete advice for fulfilling the need. A construction concept, with a tailor-made proposal according to the programme of requirements, complete with a competitive offer and time schedule. Result: The start of our further cooperation.
  • Wind pressure, snow load, internal weight, regulations, process flow and other important starting points. Our designers make their calculations with these facts in mind. Result: a reliable construction calculation.
  • The new silo plant is now being designed down to the smallest detail and worked out in workshop drawings. All details are discussed together. Resulr: After your approval, we will start production.
  • Reliability is our most important pillar. Our construction planning is therefore well thought out. We take into account the transport route and its obstacles, the (often challenging) situation at the construction site and the local capacity. Result: final planning with delivery date.
  • Led by a TSC supervisor, our experienced assembly team gets to work. We keep in regular contact about the progress in the meantime. With knowledge of local regulations and the right permits, we work safely and competently. Result: A carefully constructed new silo ready for use!
  • Every completion is a moment of celebration. We are happy to evaluate the project together. Of course, because we want to see our work in action, but also to learn from practical experience and fine-tune details where necessary. Result: a long-term partnership.
Show actions